Extension of Thiva Substation (KYT) – Phase B
In detail:
- Excavation and transportation of materials from the excavation of the foundations for the electromechanical equipment, transformer foundations, and the control building.
- Excavation and transportation of materials from the excavation of medium-voltage (MV) & low-voltage (LV) cable trenches, manholes, sealed septic tank, cable duct passages, and drainage, water supply, and sewer pipelines.
- Preparation of the final surface before applying the lean concrete for the control building and equipment foundations.
- Excavation of the substation plot to the level required for the grounding network installation.
- Backfilling, spreading, and compaction of the selected soil material to the leveling surface.
- Internal road construction.
- Asphalt paving for the remaining substation area.